- Title: Basic description of issue
- Begin with Unit/Room # or Type
- [UNIT/ROOM#] - [SHORT DESCRIPTION]
- When using the VDC Power Bi report for issue tracking, including Unit # in CI title is not required
- Include trades or components involved when possible
- e.g.
- Unit 1201 LR – SA Duct w San Plum
- Unit Type A2 MBa - FP branch w Mpipe
- Description: twofold usage
- more detailed information about the issue
- e.g. the ductwork coming off the AC closet is conflicting above ceiling in the Living Room with the sanitary line from the kitchen sink above
- Details of the assignment/correction for assignee
- e.g. Ductwork modeler to drop duct down 3" to clear sanitary and then offset back up prior to getting to popup, see markups
- Location: may be as specific as required (Power Bi report filtering allows for this)
- Be mindful of projects where they have created "Unit Type" Locations at Tier 2
- When elevating to RFI or Observation:
- drill down to lowest tier possible on the RFI or Observation
- Leave the CI at the Level/Area
- Due date: 1 day before next meeting
- Unless the modeler has agreed/committed to an earlier date, in which case use that date
- Comments: back and forth regarding the details of the assignment
- Type: these cannot be edited or changed or removed.
- Assignee(s): CI are only assigned to coordination team members or KAST On-Site Staff