Recording of original orientation training
(be aware that the Polcy outlined in the written instructions below differ from, and supercede the recording above and the recording should be used for button-clicking instructions only)
See Also KAST Subcontract and PO Award Process
Objective
To become familiar with the KAST Prequalification process and the steps necessary to complete a prequalification through the Compass online software.
KAST uses Compass Prequal to ensure that subcontractors have the financial capability to meet our standards for KAST projects. Below are the instructions for getting subcontractors pre-qualified for KAST work.
The Credit Committee reviews all prequalification requests before the project team is authorized to issue a commitment for execution. The individual requesting to issue a commitment to any subcontractor must complete the hard prequalification process. Subcontractors must be hard prequalified for every project they are on (a single prequalification does not cover the subcontractor for all projects).
For access to Compass, to have projects added, or for any other issues or concerns, please email KAST General Counsel. We recommend watching the video and reading through the tutorial before requesting assistance.
Please note that only subcontractors can edit their records in Compass; KAST cannot change these records.
Notes
You must search for the subcontractor you are trying to Soft Pre-Qualify. Once you've searched for the company name, there are four possible scenarios:



Notes
1)Sub must be
a) In Compass
i) Only the primary contact in Compass is capable of editing a subcontractor's Compass page
b) Information submitted
c) Approved KAST to view financials
i) The sub has to have approved KAST to view financials to be approved
ii) All subcontractor financials must be for the immediate prior year (e.g. 2023 financials for requests made in 2024)
iii) The requester should follow up with sub BY PHONE to ask them to approve
d) --> "Completed" in the Compass Column on the Qualification Management tab

1) Click "Create Request"
a) Choose Project
i) If the Project is not in Compass, email KAST General Counsel
b) Choose Subcontractor
if the Subcontractor is not in Compass, see the Soft Pre-Qualification section above.
c) "Approval Flow = "credit committee prequalification"
d) If requesting on someone's behalf, select them
e) Enter contract award value
f) Optional
i) Scope start
ii) Scope end
III) Required by
iv) Notes
g) Click "Create Project Approval"
i) -->adds the sub & project to the open requests
h) Upload the leveling sheet to the "Company Attachments" field located under the financials in the "General" section

2) The credit committee reviews all "open requests" every two weeks
1) Go to Project Approval Requests (as shown above)
i) This is the best way to check subcontractor status when managing multiple trades on one project
2) You will only see your requests
i) Including those done on your behalf
3) Choose either open or closed, then select your project
4) Find the sub

Once approved
1) The requester gets an email from Compass
2) Any restrictions will be emailed separately
i)Increased retainage, joint checks, monitoring plan, etc.