What is the 'Budget ROM' column in Procore's Change Event tool?
Background
The 'Budget ROM' column was designed to work with Procore's 'Budget Changes' feature and it requires the Budget and Change Events tools on your project.
Answer
The 'Budget ROM' column allows you to preview the potential financial impact (a.k.a., Rough Order or Magnitude) that a Budget Change (reallocation) might have on your project's budget. This provides value for project teams that want insight into whether a Budget Change has a positive or negative impact on your financial line items, before the Budget Change associated with those items are finalized.
By default, the value in the 'Budget ROM' column will be $0.00. If processing a Budget Change, enter the value of your reallocation within the Budget ROM column of your Change Event Line item.