Update and Upload a Project Schedule File
Objective
To update the project schedule in the native software and upload the schedule updates into Procore.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Schedule tool.
- Additional Information:
Important
If you are uploading an updated project schedule into Procore via the project level Schedule tool, make sure to use the same file name that was previously uploaded. This way the information in the Schedule Change Request History section will NOT be cleared. In addition, this will help ensure you do not have duplicate Lookahead Schedule Activities.
-
Supported File Formats:
The file types listed below can be uploaded directly:
- MPP (Microsoft Project)
- MPX (Microsoft Project, SureTrak)
- XER (Primavera P6, Primavera Contractor)
- PP (Asta Powerproject, Asta Easyplan)
- XML (Formatted for Microsoft Project, e.g. Smartsheet, OpenProject)
- XML (Primavera PMXML)
- PPX (Phoenix Project Manager)
- FTS (FastTrack Schedule)
- POD (ProjectLibre)
- GAN (GanttProject)
- PEP (TurboProject)
- PRX (Primavera P3)
- STX (Primavera SureTrak)
- CDPX (ConceptDraw PROJECT)
- CDPZ (ConceptDraw PROJECT)
- SP (Synchro Scheduler)
- ZIP (Compressed file containing one of the supported file types listed above)
Steps
- Navigate to the project's Schedule tool.
- From the Gantt view, click + Upload Schedule.
Note: You are automatically redirected to the Update Schedule page in the tool's Configure Settings.
- Select a schedule file from your computer.
- Click the Attach File link and select your schedule file.
OR
- Drag the schedule file from your computer to the Drag and Drop File area.
- Navigate to the schedule file on your computer or network, then click Open.
- Scroll to the bottom of the page and click Update.
Note:
- A "Schedule Uploaded, processing should start soon" message appears. Your schedule is placed into a job queue, and the system updates the schedule on a task-by-task basis. Depending on the number of jobs in the queue and the size of your project schedule, the overwrite process may take some time to complete. You can continue working in Procore during this process
- Important! While the schedule is being updated, it is recommended that you do not attempt to upload another schedule update. Doing so will add a second job to the queue and jobs will be processed in the order they were uploaded into the system.