Objective 

To enable Procore's financial markup capabilities on a prime contract.

Background 

You can enable financial markup capabilities on individual prime contracts. This gives your project user's the ability to apply financial markup to PCCos associated with a commitment as described in Add Financial Markup to Prime Contract Change Orders.

Things to Consider 

Steps 

  1. Navigate to your project's Prime Contracts tool.
  2. Locate the contract to work with. Then click its Number link.
  3. In the contract, click the Advanced Settings tab.
  4. Click the Edit button.
  5. Under 'Financial Markup Settings', mark the Enable Financial Markup checkbox.
  6. Click Save.