Configure the Number of Prime Contract Change Order Tiers

Objective

To configure the number of Prime Contract Change Order (PCCO) tiers for your project's Prime Contracts tool.

Background

When you initially set up the Prime Contracts tool for a project, you can choose between a 1-tier, 2-tier-, or 3-tier configuration.The settings you choose determine how many steps are required for managing change orders on the project. See What are the different change order tiers? This setting must always be configured before your project users start creating PCCOs. It is also important to note that the system will NOT permit you to change this setting once your team starts creating change orders. 

Things to Consider

  • Required User Permission:
    • 'Admin' on the project's Prime Contracts tool.
  • Important:
    • This setting MUST be set configured before you create the first Prime Contract Change Order on the project.
    • You are NOT permitted to change the change order configuration setting after the first PCCO is created.
    • If you do NOT specify a setting, Procore's default setting is the 2-tier (two-tier) configuration.
  • Additional Information:
    • To learn about the supported change order tiers in Procore,  see "What are the different change order tiers?" in the See Also section

Steps

  1. Navigate to your project's Prime Contracts tool. 
  2. Click Configure Settings .
  3. Select one of these options from the Number of Prime Contract Change Order Tiers drop-down menu:
    • 1-Tier (One-tier, a.k.a. 'single-tier')
      Users only need to create a PCCO when there is a change on a prime contract. The PCCO can then be sent to the appropriate project users for review and approval.
    • 2-Tier (Two-tier)
      This is the tool's default setting. With two tiers, your project users will first create one or more Prime Potential Change Orders (Prime PCOs). The change orders are then grouped into a PCCO, which can then be sent to the appropriate project users for review and approval.
      Note: If your company or project's billing process does NOT require you to group all of the approved change orders for the month into a single, combined change order for final signature, the two-tier configuration is the recommended setting for the Prime Contract tool. 
    • 3-Tier (Three-tier)
      With three tiers, your project users will first create one or more Prime PCOs. The change orders are then added individually or grouped into a Change Order Request (COR), which can then be submitted to the appropriate project users for review and approval. After approval, the CORs can be grouped into a single PCCO. 
  4. Click Update.