You can only void a 'Final' requirements document. If a document is 'Closed', it must be reopened.
Quantities are removed from 'Required' Inventory.
Void a Line Item
Void a Requirements Document
Navigate to the project's Materials tool.
Click the Requirements tab.
Click the requirements document name.
In the 'Items' section, click the void
icon next to the line item.
Optional: Enter notes.
Click Void Line to confirm.
Navigate to the project's Materials tool.
Click the Requirements tab.
Click the requirements document name.
Click the vertical ellipsis
for the receipt and select Void Requirement.

Optional: Enter notes.
Click Void Requirement to confirm.