Direct Issue documents must be in a 'Final' state.
If each line item is voided, the Direct Issuing document also becomes void.
Impacts after Voiding
Quantities are removed from 'Quantity Issued' and added to 'Available' Inventory.
Void a Line Item
Void a Direct Issue
Navigate to the project's Materials tool.
Click the Direct Issuing tab.
Click the direct issue number.
In the 'Items' section, click the void
icon next to the line item.
Optional: Enter notes.
Click Void Line to confirm.
Navigate to the project's Materials tool.
Click the Direct Issuing tab.
Click the direct issue number.
Click the vertical ellipsis
for the direct issue document and select Void Direct Issue.

Optional: Enter notes.
Click Void Direct Issue to confirm.