Mark a Daily Log as Complete
Objective
To mark a Daily Log as complete to verify that the information has been accurately reported and to prevent new entries or modifications from being made.
Things to Consider
- Required User Permissions:
- 'Admin' permissions on the Daily Log tool.
- Prerequisites:
- Additional Information:
- When an Admin marks a Daily Log as Complete, users are prevented from further modifying entries. At any time, an Admin can Re-open the day to make any necessary changes.
- If you want to distribute the completed daily log, there must be users added to the 'Default Distribution' list in the Daily Log tool's configure settings. See Configure Advanced Settings: Daily Log.
- The Scheduled Work log pulls live data from the project’s uploaded schedule and updates automatically.
- If the schedule changes, even after a day has been marked complete, those updates may be reflected in the log when that day is revisited.
- This ensures the log stays aligned with the most current version of the schedule.