Objective

To create automatic billing periods for requisitions. 

Background

Creating automatic billing periods saves Financial Controllers, CFOs, Project Accountants, etc. from having to go into each project every month to create billing periods. With automatic billing periods, the process only has to be completed once, and Procore will automatically open a new billing period for subcontractors on the set date until the project is complete. 

Things to Consider

  • Required User Permissions:
    • 'Admin' on the project's Commitments tool.
      OR
    • Users with 'Standard' level permissions can create a requisition only for the most recent billing period.
      Note: Even if an 'Admin' user created all billing periods for the year, a user with 'Standard' level permission (i.e., typically, the subcontractor) can only create a requisition for the last billing period in the billing period series. 
  • Prerequisites:

Steps

  1. Navigate to the project's Commitments tool.
    This reveals the Commitments page.
  2. Click the Billings tab.
    This page lists all of the commitments in the Approved and/or Complete status
  3. Click the + Start New Billing Period button in the right pane.
  4. Select the Automatic Tab.
  5. You can then select the following:
    • Frequency:
      • Monthly: If you select Monthly, select the date you want the billing period to start. 
      • Weekly
      • Never
    • Start Date: Select the date of each month you want the billing period to start. 
    • End Date: Select the date of each month you want the billing period to end.
    • Due Date: Select the date of each month you want the requisition to be due. 

      setupbilling period.png
  6. Click Save.

Next Steps

 

  • Was this article helpful?