To add a change event line item to unapproved potential change order for a prime contract.
If the Project level Prime Contracts tool is configured with the 2-tier change order configuration setting (see What are the different change order tier settings in Project Financials?), you must perform the Steps below before you can create a prime contract change order.
When do I create a potential change order? Procore recommends creating a potential change order only for any change event line item that is set to 'Out of Scope' and requires your client's or project owner's approval to proceed.
Note: If your project team is using Procore's Request for Quote (RFQ) feature, you can create a potential change order either before or after a response is submitted for an RFQ has been responded to. However, if you wait until after an RFQ response is submitted, Procore automatically populates the potential change order's Schedule of Values (SOV) with data from the RFQ.
When you create a potential change order, Procore can also be configured to automatically populate its SOV with the Rough Order of Magnitude (Revenue ROM) values. If you choose to hide the Revenue ROM feature, the value depends on the scope assigned to the change event:
Procore automatically creates the line items on the potential change order's SOV using the selected change event line items.