Skip to main content
Procore

View the Change History of an Action Plan

Objective

To view the change history of an action plan to see all changes made to the action plan in Procore.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the Project level Action Plans tool.
  • Additional Information:
    • Items cannot be deleted from the change history.
    • The change history outlines the following actions performed in Action Plans:
      • Created or deleted
        • Who create or deleted the action plan
        • The date and time of the change
      • Type is changed
        • Who made the change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Changing the location
        • Who made the change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Changing the Plan Manager
        • Who made the change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Plan approver added or removed​​​​​​​
        • Who made the change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Section is added or removed​​​​​​​
        • Who added or removed the section
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Due date is changed​​​​​​​
        • Who made changed the date
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Item added or removed​​​​​​​
        • Who made the item change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Action plan status change​​​​​​​
        • Who made the change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed
      • Title change​​​​​​​
        • Who made title the change
        • Details of the change
        • From what it was changed from and what it was changed to
        • The date and time it was changed

Steps

  1. Navigate to the Project level Action Plans tool.
  2. Click View next to the action plan you want to view the change history of.
  3. Click Change History.
    view-inspection-change-history.png