Configure Assignments Gantt View

Background

The Assignments Gantt allows you to view resource requests, resource assignments, and time off for a specific project or across all projects and people within your company. It also provides a multi-day view from one (1) day up to three (3) years.

 Important
This tutorial is for the Gantt Beta. For information for how to configure the legacy Gantt view, see View Assignments Gantt.

Things to Consider

Steps

Adjust List and Timeline Ratio

  1. Navigate to the Company level Resource Planning tool.
  2. Click Assignments and select Gantt (Beta).
  3. Hover over the divider that separates the grid and the graph.
  4. Click the divider and move it to the desired location using a drag-and-drop operation.
    adjust-width.png

Group by Project or Resource

  1. Navigate to the Company level Resource Planning tool.
  2. Click Assignments and select Gantt (Beta).
  3. Select to see information grouped by Resources or Projects.
    new-gantt-resource-project-picker.png

Configure Displayed Information

  1. Navigate to the Company level Resource Planning tool.
  2. Click Assignments and select Gantt (Beta).
  3. Click the table settings icon-ag-grid-table-filter-menu.png icon.
  4. Move the toggle to the ON icon-toggle-on.png position or OFF icon-toggle-on.png position to show or hide details in the Gantt bars for the following:
    • Project Information
    • Allocation Information 
    • Time Off Information
    • Hide Weekends
  5. Click and move the slider using a drag-and-drop operation to adjust the size for the following settings:
    • Row height in the Gantt 
    • Task Border Radius

Expand and Collapse Projects, Categories, and Subcategories

  1. Navigate to the Company level Resource Planning tool.
  2. Click Assignments and select Gantt (Beta).
  3. Next to the project, category, or subcategory, take one of the following actions:
    • Click the expand collapse-caret.png icon to expand the information
    • Click the collapse  expand-caret.png icon to collapse the information
 Tip
To expand and collapse all projects, click the expand icon-vertical-carets-expand.png or collapse icon-vertical-carets-collapse.png icon next to 'Project Name'.

View Timeframe, Zoom In and Out

  1. Navigate to the Company level Resource Planning tool.

  2. Click Assignments and select Gantt (Beta).

  3. Configure your timeframe:

    • Select the date, and select the timeframe from the neighboring dropdown menu.

    • Click the zoom in Icon Zoom In Magnifying Glass icon or zoom out Icon Zoom Out Magnifying Glass icon to view the Gantt from a single day, up to many years.

See Also