Import a Prime Contract into Procore from Workday®

Objective

To import and sync data between a Prime Contract in Workday® and Procore. A Prime Contract must be imported from Workday® to Procore before financial data for that contract can be synced between the two systems.

Background

A Prime Contract must be imported from Workday® to Procore before financial data for that contract can be synced between the two systems. Importing a Prime Contract from Workday® creates a Prime Contract in Procore, but does not create any financial information within that contract. Because the contract's financial data will export to Workday® as a single, summarized line item, you must create the schedule of values for your contract within Procore. 

Things to Consider

Steps

  1. Navigate to the Company level ERP Integrations tool. 
  2. Click the Prime Contracts tab. 
  3. Click the Ready to Import link in the right sidebar. 
  4. Locate the desired project's prime contract in the Prime Contracts Ready to be Imported list. 
  5. Click Add to Procore
    A message in GREEN text confirms when your prime contract has been added to Procore. 
  6. Line items added to the contract SOV in Procore will automatically sync to Workday® as a single, summarized line item.