Common Questions Sage 300 CRE

Issue Description
How to unlink a Commitment synced with Sage 300 CRE® If you need to unlink and retrieve/make a correction to a Commitment after it has been synced between Procore and Sage 300 CRE® 
How to delete a Commitment synced with Sage 300 CRE® If you want a PO or Subcontract deleted from Procore after it’s been synced with Sage 300 CRE®
How to unlink a CCO synced with Sage 300 CRE® If you need to unlink and retrieve/make a correction to a CCO after it has been synced between Procore and Sage 300 CRE®
How to delete a CCO synced with Sage 300 CRE® If you want a CCO deleted from Procore after it has been synced with Sage 300 CRE®
How to unlink a PCCO synced with ERP If you need to unlink and retrieve/make a correction to a PCCO after it has been synced between Procore and Sage 300 CRE®
How to unlink a Subcontractor Invoice synced with ERP If you need to unlink and retrieve/make a correction to a Subcontractor Invoice that is synced between Procore and Sage 300 CRE®
How to unlink a vendor synced with Sage 300 CRE® If you need to unlink a synced vendor from Procore ERP Integrations Tab
Can I merge an existing Sage 300 CRE® project with a Procore project? Projects that are in-progress or created before connection of the integration cannot be synced. Professional Services for assistance with integrating in-progress/pre-existing project records are available for an additional fee.
Why are there duplicate company records in Procore’s Company Directory If two of the same company in your Procore directory exist and you want to know how to merge these into one synced vendor 
How to add new cost codes or cost types to Procore If you need to add a new cost code or cost type to Procore 
How to resolve 'Import operation took longer than the set timeout' error If you are receiving the error 'Import operation took longer than the set timeout'.