Enable ERP Job Cost Transaction Syncing on a Procore Project

ERP DOCUMENTATION

Each Procore-built ERP integration offers its own unique feature set. Your integration might not support the action described on this page.

To learn about your integration and its supported features, see Things to Know About Your ERP Integration.

To explore all documentation for your integration, see ERP Integrations.

Objective

To enable the job cost transaction syncing setting on a Procore project for companies using supported ERP integrations.

Background

If your company's Procore account is integrated with an ERP system that supports this feature, you can import job cost transaction data from your ERP. Once imported, the values of those transactions can be viewed in the 'Direct Costs' column on a budget line item in a Procore project.

Users who are assigned the appropriate granular permission can click the values in the 'Direct Costs' column in the budget tool to open a window showing detailed information about the item.

Things to Consider

Steps

  1. Navigate to the project's Admin tool. 
  2. Under 'Project Settings', click General.
  3. Scroll to 'Advanced'.
  4. Mark the checkbox to Enable ERP Job Cost Transaction Syncing.
    This action enables the syncing feature in the project.
  5. Click Update.

Next Steps

See Also