Objective

To delete project cost codes from a Procore project that has previously been synced with your ERP system.

Background

If your company's Procore account is integrated with an ERP system, you can delete Project Cost Codes if they are not be in use on any items in the project.

Things to Consider

Steps

To delete unused cost codes from the project's 'Cost Code' segment: 

  1. Navigate to the Project level Admin tool. 
  2. Under 'Project Settings', click the Work Breakdown Structure link.
  3. In the 'Segments' table, click the segment that contains the item(s) to delete. 
    wbs-project-segments-edit.png
     
  4. Locate the segment item to delete. If you are deleting a tiered segment, you will want to navigate to the segment item and highlight it in the left pane. 
  5. Click the vertical ellipsis on the segment item's line item, and choose Delete from the Overflow menu. 

    wbs-delete-segment-item.png