Add ERP Standard Cost Codes to a Project

Objective

To add ERP Standard Cost Codes' at the Company level to a 'Project Cost Codes' list in Procore.

Background

Cost codes need to be added to a project for use with Procore's financial tools, and your ERP integration. 

Things to Consider

Steps

  1. Navigate to the Project level Admin tool.
  2. Under 'Project Settings', click the Work Breakdown Structure link. 
  3. In the 'Segments' list, click the Cost Codes link.
  4. Click the Cost Codes from Company button. 
    btn-cost-codes-from-company.png
  5. In the 'Add Cost Codes to this Project' window, choose from these options:
    add-cost-codes-window.png
    • To copy all of your company's cost codes to the project, click the Select All Cost Codes button. 
    • To copy only selected cost codes, expand and collapse the desired segment items and then highlight the segment items to copy. 
  6. Click the Add button. 