Export a PCCO as an OCO to CMiC

Objective

To export a Prime Contract Change Order (PCCO) as an Owner Change Order (OCO) to CMiC.

Background Edit section

During a construction project, you will often create prime contract change orders. When a PCCO is created in Procore, you might need to export it as an OCO to CMiC. Follow the steps below to export a Procore PCCO as an OCO to CMiC. 

Things to Consider Edit section

Steps

  1. Navigate to the project's Admin tool. 
  2. Under 'Project Settings', click General.
  3. Scroll to 'Advanced'.
  4. Mark the checkbox to Create Owner Change Orders.
  5. Click Update.
  6. Complete the steps in Export a PCCO to ERP.