Add Company Cost Codes

Objective

To add a cost code to the 'Cost Code' segment in your Company level Work Breakdown Structure (WBS)

Background

In Procore's WBS, there is is a default segment named 'Cost Code' that is available in the 'Segments' table of the Company Admin tool. This segment contains individual segment items, commonly known as cost codes. A cost code is a series of alphanumeric characters used to represent the different labor and material costs for a specific type work being performed on the job. Your cost codes are used to manage the dollar amounts and quantities on a project's budget. 

By default, Procore's 'Cost Code' segment contains cost codes that align with the CSI MasterFormat. To learn more, see What are Procore's default cost codes?

Things to Consider

Steps

  1. Navigate to the Company level Admin tool. 
  2. Under 'Company Settings', click the Work Breakdown Structure link. 
  3. In the 'Segments' table, click the 'Cost Codes' segment.
  4. In the tree structure on the left side of the page, highlight the root folder named Cost Codes.
  5. To add cost codes to the 'Cost Codes' tree, navigate to the parent branch where you want to add the new child code.
    • Click the Add Items button.
    • Complete this data entry:
      • Code
        Enter a unique alphanumeric code for the segment item. In this example, we are creating tiered cost codes to align to Procore's default cost code list which aligns with the CIS MasterFormat, so we will enter: 012000
      • Description
        Enter a description of the segment item. In this example, we are creating tiered cost codes to align to Procore's default cost code list which aligns with the CIS MasterFormat, so we will enter: Furnishing 
  6. Repeat the steps above for every tier and all the cost codes that you want to add to the segment. 

Next Steps

See Also