Category Name |
Description |
Sample RFI |
Scope clarification |
Anytime something may be missing, added, changed or inconsistent in the project scope. |
Per the structural drawings, there is no footer shown beneath the partition wall running along E-Line. The architectural drawings show a footer supporting the wall at this location. Please confirm which is correct. |
Coordination issue |
A spatial conflict between two or more NEW elements being installed in the building. If you have a conflict with an existing item it would be an "Unforeseen / Existing Condition". |
Please clarify if it is acceptable for some of the above gallery MEP systems to be below the bottom chord of the trusses. The attached screenshots and nwd file show a lack of space to coordinate the duct-work, roof drain, overflow drain, and mechanical piping within the joists. |
Missing information |
Any information that should be available, but is missing from the drawings and/or specs. |
The specifications do not provide specs for the door labels. Please provide a detail or specification for the door labels. |
Field issue |
An error made while installing something, which now requires guidance from the design team to either approve a fix, or come up with a fix. |
An excavator accidentally hit and bent (2) anchor rods. The other (3) rods at each location were not impacted. Please advise if it is structurally acceptable to straighten by either a cold bend or heated method as long as the rods are not bent less than 45 degrees from plumb. |
Constructability issue |
A drawing or specification cannot be built as shown, for reasons which are not spatial in nature. If you have a spatial issue it would be a "Coordination Issue". |
The hinge detail will not work as drawn; the hinge cannot be anchored to the stone apron because it will crack and fail. Please see the proposed hinge detail that is attached and advise if this is acceptable. |
Substitution request |
A drawing or spec works as shown, however the contractor is requesting to substitute a product or detail. |
Light fixture L-05 is currently backordered for at least 12 weeks. We recommend substituting with the roughly equivalent fixture provided in the attachment in order to keep the construction schedule. Switching to this fixture would be a no cost change. Please advise if this is acceptable. |
Unforeseen/Existing Condition |
A condition is discovered in the field which was not shown or designed in the drawings. |
The existing steel column at the new entry is not oriented as shown in the plan. This will change the connection between the concrete detail to the steel column. We suggest filling the whole flange space with concrete for ease of forming. Please advise how to proceed. |
Unknown |
Any RFI that we can’t match to a category will be labeled as unknown. |
Please see the attached PDF and advise. |