If you notice that the Budget or Budget Modifications are not showing up in Sage 300 CRE® after exporting, you may need to post the Import Estimates batch in Sage 300 CRE® Job Cost. Follow the instructions below to remedy the issue.
After a successful export in Procore, you must manually post the entries.
Once your batch is posted, you will see the budget changes in Inquiries and Reports. See the Sage 300 CRE® Help for further instructions on posting batches.
If these steps do not resolve your issues, please contact Support with details of which error you have been receiving and which steps you have already tried along with the exact outcome.