Yes. If you are a Procore Administrator or if you have 'Admin' permissions on the project's Admin tool, your company's Procore Administrator (or a user with 'Admin' level permissions on the Project Admin tool) can enable the Change Events tool. However, before enabling the tool, it is important to follow the steps below:
Before enabling the Change Events tool, determine if any change orders have been created on the project. To view a list of change orders on a project, follow these steps: View Change Orders.
If you discover that your users have already created change orders on the project, your company's Procore Administrator or a user with 'Admin' level permissions on the project's Admin tool must send an email to your company's Procore point of contact requesting to run Procore's change order migration process on your project.
The purpose of the migration process is:
This step is performed for you by Procore. Your Procore point of contact will notify you when the migration process is complete.