BIM/VDC RFI Process
Process for Coordination RFIs, particularly when they come from our 3rd party modelers. First, the RFI Manager should always remain a KAST APM/PE, not be changed to a VDC Manager.
- VDC Manager receives RFI from 3rd party
- vets the RFI
- If valid, re-writes RFI in Procore to match KAST standard
- Set status to “draft”
- Add any pertinent attachments from 3rd party
- Add self to "distribution"
- Use “email” tool in RFI to send to RFI Manager for forward to A/E
- RFI Manager processes RFI
- Set assignees (architect is always required assignee)
- Add distribution (typically KAST and Owner)
- Ensure that VDC Manager is on distribution
- Create as “open”
- A/E adds response
- RFI manager and all on distribution will get notified of response
- VDC manager will get notified (if on distribution) and review
- Use “email” tool in RFI to notify RFI Manager as to whether response valid or not
- If Valid, RFI Manager marks response as “official” and sends out to subs using “email” tool in RFI
- If not Valid, VDC Manager to add response with clarification
- Use "email" tool on RFI to forward to subs if not sure
- "official response" must be checked for sub to see it
- Process starts at 1e again
- RFI Manager needs to change Ball in Court back to Assignee
- Use "email" tool on RFI to forward to subs if not sure