Objective

To view a labor budget to actual report on an Android mobile device.

Background

The Labor Budget to Actual Report compares the hours recorded in the Timesheets tool to the imported Budgeted Hours at a cost code level. The report is broken down by cost code and includes % of hours used, budgeted hours, job to date hours, and remaining hours.

Things to Consider

  • Required User Permission:
    • 'Read-only' or above on the project's Reports tool.
      AND
    • 'Read-only' or above on the project's Timesheets tool.

Steps

  1. Navigate to the Timesheets tool on an Android mobile device.
  2. Tap Reports (2018-04-17_16-44-12.png).
    This reveals the project's Labor Report (see image below).

    2018-04-17_16-44-44.png
     
  3. To return to the Timesheets tool, tap the back arrow.