Objective

To edit the schedule of values of a commitment that is a purchase order from an Android mobile device.

Things to Consider

  • Required User Permission:
    • Required User Permission:
    • To edit a purchase order or subcontract, 'Admin' level permission on the project's Commitments tool.
      OR
    • To edit a purchase order or subcontract as a user with 'Standard' or 'Read Only' level permission to the Commitments tool, the 'Update Purchase Order' and 'Update Subcontract' granular permissions must be enabled on the permission template associated with your user account on the project. See Grant Granular Permissions in a Permission Template.
  • This asset/item can be viewed or edited in offline mode provided that the asset/item was previously viewed and cached on your mobile device.

Steps

  1. Navigate to the project's Commitments tool on an Android mobile device.
  2. Tap the purchase order to which you want to add a line item.
  3. Tap Schedule of Values.

    2018-03-29_13-59-37.png
     
  4. Tap the item you want to edit.
  5. Tap Edit (2018-06-13_11-05-20.png).
  6. Tap into a field to modify the appropriate information.
  7. Tap Save.
  • Was this article helpful?