Clone a Change Event

Objective

To clone a change event so you do not need to manually recreate it. 

Things to Consider

  • Required User Permission: 'Admin' on the project's Change Events tool.

Steps

  1. Navigate to the project's Change Events tool.
  2. Click View next to the change event you would like to clone.
  3. Click the Clone button in the right sidebar.
    You will be taken to the cloned change event with the following information copied over from the first change event:
    • Type
    • Description
    • Attachments
    • Title
    • Scope
    • Change Reason
    • Cost Code
    • Cost Type
    • Description
    • Vendor
    • Contract