Skip to main content
Procore

2016

This pages lists the notable changes for the Company level Schedule tool for 2016.

Added Milestone Filter To Schedules Tool (10/25/2016) 

Updated the Project and Company-level Schedule tool to add a new 'Milestone' filter to the All, Day, Week, and Month Views.

Link Scheduled Tasks from P6 and Microsoft Project to a Submittal (2/15/2016)

Users now have the ability to link a scheduled task from Primavera (P6) and Microsoft Project to a submittal. This assists users who rely on the Master Schedule when creating a project's submittal schedule understand how material submittals might impact the critical path and project milestones