What data is synced between Viewpoint Vista and Procore?

 

Answer

The following data fields are synchronized between Viewpoint Vista and Procore:

  • Cost Codes
  • Cost Types
  • Vendors
  • Job-to-Date Costs and Units
  • Month-to-Date Costs and Units
  • Account Payable Dollars Paid
  • Original Estimate
  • Commitments
  • Commitment Change Orders

Notes:

  • Job names are not synchronized because some companies have longer project names in Procore than what is allowed in Viewpoint Vista.
  • Viewpoint Vista treats Sub Jobs as Jobs, so Procore's sub job concept is not supported with the integration.