Skip to main content
Procore

What data is synced between Sage and Procore?

The following data fields are synchronized via the Sage 300 CRE Connector:

  • Cost codes
  • Cost types
  • Vendors
  • Job-to-date costs and units
  • Month to date costs and units
  • Account Payable Dollars paid
  • Cost estimate (budget)
  • Commitments
  • Commitment Change Orders

 

Note: Job names are not synchronized because some users have longer project names in Procore than what is allowed in Sage.

 